Up until the snow storm in early February, preparations for the geophysical survey of the Dalecarlia Parkway/DC right-of-way area continued. The team continued removal of underbrush and bamboo as well as the clearance of any metallic surface debris. During the surface clearance, two munition debris items, both from 75 mm munition items were recovered. Neither posed any hazard to workers or the community.
Spring Valley Project Monthly Update
February 2010