Jun 25, 2013

Cleanup Site Field Work Continues Regardless of Impending Furlough

Engineering Control Structure (ECS) being built
In preparation for the high probability excavation work, the site construction team began building the Engineering Control Structure (ECS).  The construction of the tent will continue into July ... Although the high probability operations have been delayed due to the upcoming furlough, the site crew will continue to prepare the site so we are ready to begin high probability operations after the furlough ends.  
 
Chemical Agent Filtration System (CAFS)
It is important to note that field work will not halt at the site.  Upcoming site work will include completing the installation of the ECS, installing the remaining engineering controls, performing on-site training for the high probability excavation teams, and performing the pre-operational surveys and testing. 
Spring Valley FUDS
Project Update
June 2013

Jun 17, 2013

Sequester Delays Glenbrook Road High Probability Work Until Fall

The U.S. Army Corps of Engineers, Baltimore District, has decided to modify the work schedule for high probability operations at 4825 Glenbrook Road ... The furlough will restrict the team to four 8-hour work days per week and overtime compensation will not be allowed, which restricts available work hours from our current schedule of 60 hours per week down to 32 hours per week ... Even the slightest potential that response capabilities might be degraded under furlough conditions led to the decision to delay high probability intrusive activities at the site.
U.S. Army Corps of Engineers
Press Release
June 17, 2013
Recently, the Department of Defense published its furlough implementation guidance that directs the Military Departments to start furloughing their civilian work force.  The furlough period will begin the week of July 8 and continue for 11 weeks ... Given this guidance, COL J. Richard Jordan, III, Commander and District Engineer at the Baltimore District has made the decision to delay the start of the high probability work at 4825 Glenbrook Road during the proposed Department of Defense furlough period which is scheduled to end on September 21, 2013 ... Should the period of furloughs be shortened, we will quickly re-assess the schedule and begin work as soon as possible. 
Brenda Barber, Project Manager
Glenbrook Road Update
June 17, 2013
 