This week crews continued the installation process for the trench to support utility relocation at the site. Utility relocation will take approximately two more weeks ... As an added layer of safety, air monitoring was used during all excavations ... During the week of April 8, crews will relocate and re-establish the sewer line. The water line will be relocated and re-established the week of April 15.
We anticipate starting the high probability excavation work this summer ... Recently we have had weather delays and issues related to the relocation of the site utilities ... Due to the deeper location of the utilities more expansive trenches are required, which increases the complexity of the work ... Crews will work some limited Fridays and Saturdays from now until June to make up for the schedule delays to minimize an impact to the completion of the project.
4825 Glenbrook RoadWeekly Update
April 5, 2013
No comments:
Post a Comment