"Construction began on the South Extension [of the Emergency Containment Structure] and continues into September ... The South Extension’s construction is expected to take 6 weeks, and should be completed in mid September. The digging investigation inside the South Extension will be short; 1 - 2 weeks is anticipated. During this time the Shelter-in Place program will go into effect again for those residents and workers within 750 feet of the project area, Monday - Friday from 8 a.m. – 4 p.m."
Spring Valley FUDS
Monthly Project Update
August 2008
Aug 31, 2008