4825 Glenbrook Road
Weekly Update
September 19, 2014
This month crews continued preparing the site for the Engineering Control Structure (ECS) move, including unlacing the ECS tent’s "skin," and building a dirt ramp to access the low probability work area behind the back retaining wall ... The crane is being used to move heavy equipment into place, especially the large ECS tent frame, in preparation for Phase 2 of the high probability excavation effort. On September 22, the crane passed the load test, demonstrating it will be able to move the large ECS tent frame from the front of the property towards the back, starting on October 3rd.
Spring Valley FUDS
Project Summary
September 2014
b.jpg)