Weapons of Mass Destruction in DC
Jun 25, 2013
Cleanup Site Field Work Continues Regardless of Impending Furlough
›
Engineering Control Structure (ECS) being built In preparation for the high probability excavation work, the site construction team bega...
Jun 17, 2013
Sequester Delays Glenbrook Road High Probability Work Until Fall
›
The U.S. Army Corps of Engineers, Baltimore District, has decided to modify the work schedule for high probability operations at 4825 Glenbr...
May 27, 2013
Suspect Test Tube Halts Intrusive Excavations at Cleanup Site
›
Late in the afternoon on Tuesday, May 21, the site crew encountered a suspect closed container item during our excavation behind the ret...
2 comments:
May 22, 2013
Augered Hole Uncovers Empty Cavity 75-Millimeter Munition
›
The Spring Valley munitions cleanup project recently uncovered an empty 75-millimeter shell and small pieces of glassware, which the Army Co...
Apr 9, 2013
Preparations Continue for Erection of "Engineering Control Structure"
›
The Corps of Engineers will use a large (60 feet by 82.5 feet) Engineering Control Structure (ECS) with a Chemical Agent Filtration System (...
Apr 5, 2013
Start of Glenbrook High Probability Digging Postponed until Summer
›
Work has begun at the university-owned site ( 4825 Glenbrook Road ) for what is hoped will be the final phase of the effort to find and ...
Mar 28, 2013
EPA Admits It Cannot Enforce Provisions of Executive Order
›
EPA recognizes the entirely understandable concern that your clients and their parents have regarding USACE's cleanup work so close to ...
‹
›